MU
Equipment HealthUtilitiesK-168

Compressor K-168

Medium Criticality

K-168 · Compressor · Utilities / Compressor Area 3 · Mfr. Sulzer

Health trend declining
40%

Critical

Failure Probability

67%

Anomaly Score

54

Remaining Useful Life

84 Days

RUL Confidence

76%

Health, Vibration & Temperature Trend

Trailing 30 days · sensor-fused signal

Remaining Useful Life

Generated by the Remaining Useful Life Agent

84

days

Remaining Days

2,016

hrs

Operating Hours

651

cycles

Remaining Cycles

76

%

Confidence

Likely failure mode: Fouling

Maintenance Strategy Optimization

Current strategy: maintenance every 36 months

From

36mo

To

33mo

Advance Schedule

Accelerated degradation detected — vibration and anomaly score trending above baseline faster than model expectation.

Asset Details

Equipment IDEQ-K-168
Functional LocationUtilities / Compressor Area 3
ManufacturerSulzer
Install Date2016-10-15
Runtime Hours28,711 hrs
Last Maintenance2026-01-23
Next Maintenance2026-10-13

AI Recommendation

Maintenance Recommendation Agent

K-168 shows accelerating degradation. Recommend scoping into the next available shutdown window and pre-ordering fouling spares.

Recommended Shutdown

Shutdown Planning Agent

Utilities Boiler Emergency Repair

Starts 2026-08-09 · 2 days

Recent Work Orders

WO-20450 · Vibration inspection

Closed · 2026-01-23

WO-20451 · Lubrication top-up

Closed · 2026-01-23

WO-20452 · Bearing replacement

Closed · 2026-01-23