Hydrocracker Major Turnaround

Turnaround ShutdownMedium Risk

SD-2026-014 · Hydrocracker · 2026-09-05 · 10 days

Budget

$4.20M

Production Loss/Day

$640K

Completion Probability

87%

Manpower Coverage

99%

Shutdown Timeline

9 jobs scoped across 10 days

Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
Day 9
Day 10
Day 11
P-101
14h
K-102
16h
R-106
25h
CV-120
16h
EP-122
43h
GB-126
25h
E-133
60h
FN-135
61h
F-137
13h
Critical
Inspection
Statutory
AI Recommended
Preventive

Job Breakdown

P-101

Instrument Team · 14h

Critical

K-102

Instrument Team · 16h

Critical

R-106

Contractor - Turnaround Services · 25h

Statutory

CV-120

Mechanical Team B · 16h

AI Recommended

EP-122

Rotating Equipment Team · 43h

Critical

GB-126

Mechanical Team A · 25h

Critical

E-133

Rotating Equipment Team · 60h

Inspection

FN-135

Instrument Team · 61h

Statutory

F-137

Electrical Team · 13h

AI Recommended