Shutdown PlanningSD-2026-015
BackFCC Wet Gas Compressor Overhaul
Unit ShutdownHigh RiskSD-2026-015 · FCC Unit · 2026-08-24 · 5 days
Budget
$1.15M
Production Loss/Day
$520K
Completion Probability
79%
Manpower Coverage
95%
Shutdown Timeline
7 jobs scoped across 5 days
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
T-107
49h
K-108
8h
GB-119
54h
C-121
42h
BR-136
67h
BR-140
64h
E-146
9h
Critical
Inspection
Statutory
AI Recommended
Preventive
Job Breakdown
T-107
Electrical Team · 49h
K-108
Contractor - Turnaround Services · 8h
GB-119
Electrical Team · 54h
C-121
Rotating Equipment Team · 42h
BR-136
Mechanical Team B · 67h
BR-140
Instrument Team · 64h
E-146
Contractor - Turnaround Services · 9h