CDU Preheat Train Inspection

Minor ShutdownLow Risk

SD-2026-016 · CDU · 2026-09-29 · 3 days

Budget

$380K

Production Loss/Day

$410K

Completion Probability

94%

Manpower Coverage

92%

Shutdown Timeline

6 jobs scoped across 3 days

Day 1
Day 2
Day 3
Day 4
E-103
8h
F-104
10h
C-105
45h
GB-124
27h
CV-131
38h
F-145
51h
Critical
Inspection
Statutory
AI Recommended
Preventive

Job Breakdown

E-103

Rotating Equipment Team · 8h

Critical

F-104

Instrument Team · 10h

Inspection

C-105

Contractor - Turnaround Services · 45h

Statutory

GB-124

Contractor - Turnaround Services · 27h

AI Recommended

CV-131

Mechanical Team B · 38h

Preventive

F-145

Rotating Equipment Team · 51h

Critical