Shutdown PlanningSD-2026-016
BackCDU Preheat Train Inspection
Minor ShutdownLow RiskSD-2026-016 · CDU · 2026-09-29 · 3 days
Budget
$380K
Production Loss/Day
$410K
Completion Probability
94%
Manpower Coverage
92%
Shutdown Timeline
6 jobs scoped across 3 days
Day 1
Day 2
Day 3
Day 4
E-103
8h
F-104
10h
C-105
45h
GB-124
27h
CV-131
38h
F-145
51h
Critical
Inspection
Statutory
AI Recommended
Preventive
Job Breakdown
E-103
Rotating Equipment Team · 8h
F-104
Instrument Team · 10h
C-105
Contractor - Turnaround Services · 45h
GB-124
Contractor - Turnaround Services · 27h
CV-131
Mechanical Team B · 38h
F-145
Rotating Equipment Team · 51h