Shutdown PlanningSD-2026-017
BackSulfur Recovery Statutory Inspection
Campaign ShutdownLow RiskSD-2026-017 · Sulfur Recovery Unit · 2026-10-14 · 4 days
Budget
$290K
Production Loss/Day
$90K
Completion Probability
96%
Manpower Coverage
89%
Shutdown Timeline
5 jobs scoped across 4 days
Day 1
Day 2
Day 3
Day 4
Day 5
V-112
19h
P-143
42h
BL-144
14h
PL-155
25h
CV-176
32h
Critical
Inspection
Statutory
AI Recommended
Preventive
Job Breakdown
V-112
Electrical Team · 19h
P-143
Rotating Equipment Team · 42h
BL-144
Rotating Equipment Team · 14h
PL-155
Contractor - Turnaround Services · 25h
CV-176
Contractor - Turnaround Services · 32h