Hydrocracking Reactor R-201
High CriticalityR-106 · Reactor · Hydrocracker / Reaction Section · Mfr. Ebara
Healthy
Failure Probability
16%
Anomaly Score
15
Remaining Useful Life
224 Days
RUL Confidence
77%
Health, Vibration & Temperature Trend
Trailing 30 days · sensor-fused signal
Remaining Useful Life
Generated by the Remaining Useful Life Agent
224
days
Remaining Days
5,376
hrs
Operating Hours
1,806
cycles
Remaining Cycles
77
%
Confidence
Likely failure mode: Catalyst Deactivation
Maintenance Strategy Optimization
Current strategy: maintenance every 18 months
From
18mo
To
18mo
Equipment tracking within expected degradation envelope.
Asset Details
AI Recommendation
Maintenance Recommendation Agent
R-106 is tracking within its expected envelope. No immediate action required; continue routine condition monitoring.
Recommended Shutdown
Shutdown Planning Agent
Hydrocracker Major Turnaround
Starts 2026-09-05 · 10 days
Recent Work Orders
WO-20450 · Vibration inspection
Closed · 2026-02-01
WO-20451 · Lubrication top-up
Closed · 2026-02-01
WO-20452 · Bearing replacement
Closed · 2026-02-01