Reactor R-152
High CriticalityR-152 · Reactor · Hydrocracker / Reactor Area 4 · Mfr. Weir Group
Attention
Failure Probability
34%
Anomaly Score
35
Remaining Useful Life
153 Days
RUL Confidence
78%
Health, Vibration & Temperature Trend
Trailing 30 days · sensor-fused signal
Remaining Useful Life
Generated by the Remaining Useful Life Agent
153
days
Remaining Days
3,672
hrs
Operating Hours
522
cycles
Remaining Cycles
78
%
Confidence
Likely failure mode: Internal Corrosion
Maintenance Strategy Optimization
Current strategy: maintenance every 18 months
From
18mo
To
18mo
Equipment tracking within expected degradation envelope.
Asset Details
AI Recommendation
Maintenance Recommendation Agent
R-152 is tracking within its expected envelope. No immediate action required; continue routine condition monitoring.
Recommended Shutdown
Shutdown Planning Agent
Hydrocracker Major Turnaround
Starts 2026-09-05 · 10 days
Recent Work Orders
WO-20450 · Vibration inspection
Closed · 2026-03-27
WO-20451 · Lubrication top-up
Closed · 2026-03-27
WO-20452 · Bearing replacement
Closed · 2026-03-27