Power Recovery Turbine
High CriticalityT-107 · Turbine · FCC Unit / Power Recovery · Mfr. Elliott Group
Attention
Failure Probability
18%
Anomaly Score
22
Remaining Useful Life
180 Days
RUL Confidence
74%
Health, Vibration & Temperature Trend
Trailing 30 days · sensor-fused signal
Remaining Useful Life
Generated by the Remaining Useful Life Agent
180
days
Remaining Days
4,320
hrs
Operating Hours
946
cycles
Remaining Cycles
74
%
Confidence
Likely failure mode: Bearing Wear
Maintenance Strategy Optimization
Current strategy: maintenance every 18 months
From
18mo
To
18mo
Equipment tracking within expected degradation envelope.
Asset Details
AI Recommendation
Maintenance Recommendation Agent
T-107 is tracking within its expected envelope. No immediate action required; continue routine condition monitoring.
Recommended Shutdown
Shutdown Planning Agent
FCC Wet Gas Compressor Overhaul
Starts 2026-08-24 · 5 days
Recent Work Orders
WO-20450 · Vibration inspection
Closed · 2026-04-09
WO-20451 · Lubrication top-up
Closed · 2026-04-09
WO-20452 · Bearing replacement
Closed · 2026-04-09